Site Preparation And Grading Criteria
INTRODUCTION
These criteria are established to provide uniform construction practices and method to
cover contingencies associated with the unknowns of subsurface conditions.construction
documents are prepared in a manner to establish directives that minimize post-
construction negotiations on normal construction projects. We can be defined as the legal
entity or its representative responsible by contract to the State Government for the
construction of a state project. Design and construction administration are the our sole
responsibility . The Physical construction of the project is also our the sole
responsibility as a Contractor of the projects.
DIRECTIVES
- We have a clear definition of the our responsibilities for the
construction.
- We Specify a complete extent of contract work established by professional
evaluation and study of conditions relative to construction of the project. The
information presented to us is used by us for preparation of bids for the construction.
- Some times the geotechnical report which contains recommendations that are
intended to be for used. We incorporate these recommendations that deems appropriate into
the project specifications as specific directives. The geotechnical report is included, in
its entirety, in the project specification manual with a clear admonition that it is
included for our information only.
SITE INVESTIGATION
- Upon obtaining a design contract, we shall observe the project sited
conditions and existing site information (past site history) to establish the need for
additional site information on surface and subsurface conditions.
- A ground control survey is included, but not be limited to, the
establishment of property lines, existing structures, easements, rights-of-way, above
& below ground utilities, vertical control with relative elevations, and horizontal
control with relative coordinates. Necessary points are established and marked at the site
to provide adequate construction control for the project (benchmarks, coordinate control
points, baselines, etc.). The site survey and subsequent site plans shall depict any
floodplain encroachment.
- A subsurface exploration scope shall is established with input from the
providing firm, the Designer, and the Designer's civil & structural consultants. The
subsurface exploration consist of, but not be limited to, adequate soil borings to
establish subsurface criteria and site construction directives. The foundation report
includes a location of all soil tests and borings made, an establishment of soil
classifications in accordance with the Unified Soil Classification System (ASTM D 2487),
ground water conditions, soil compaction recommendations, soil support estimates with
settlement projections from loads, and deep support system recommendations when required
by engineering judgment. The site Class, per NC Code Chapter 16 seismic provisions, shall
be determined.
- Presumptive Load-Bearing Values: Presumptive load-bearing values may be
used only when the project configuration falls within all Chapter 18 NC Code limitations
for use of such values.
ROCK EXCAVATION
- Rock excavation shall be specified in a manner to be fair . It is important
to study the soil investigation report to establish the problems expected in the
excavation and grading at the site.
- When conditions indicate the possibility of rock excavation, provide a
clear and concise definition of each type of rock excavation expected for the project.
Rock types may include categories such as Mass Rock, Trench Rock, Caisson Rock, etc. It is
important to provide definitions on a project-specific basis.
- Specify a realistic quantity of rock material that must be included by
Sharma Construction in the base bid for each type of rock excavation. The specifications
and Forms of Proposal are structured to accommodate the differing contractual arrangements
that may result depending upon the award of the project contract under the Single-Prime or
Multiple-Prime options.
- The Designer may provide a method in the specifications that the Sharma
Construction may use to prove that material should be classified as rock excavation. The
specifications may be written to allow the Sharma Construction to provide a
demonstration that, for example, the material cannot be ripped with a crawler tractor
rated at a minimum of 50,000 pounds drawbar pull at one mile per hour, pulling a
single-tooth ripper. Similarly, for Trench Rock, the Sharma Construction may provide
a demonstration that, for example, the material cannot be removed with a backhoe equipped
with a minimum ½ cubic yard heavy-duty trenching bucket placed on a machine capable of a
lifting capacity of 7,500 pounds at a trench depth of 10 feet. Such specifications should
state that the Contractor may be required to provide the demonstration equipment's
specification data verifying the minimum equipment ratings and that the equipment shall be
in good repair and proper working condition.
UNSUITABLE SOIL MATERIAL
- When the soil investigation report or engineering judgement based on site
visit indicates unsuitable soil material may be encountered below design elevations, a
reasonably estimated base bid quantity of unsuitable soil shall be stated in the
specifications.
- A unit price shall be solicited as the basis of adjustment of the final
contact cost. The specifications must clearly indicate that the unit price includes the
excavation of the unsuitable soil, the appropriate offsite disposal of the unsuitable
material, its replacement with satisfactory (per the project specifications) soil, and
that replacement soil placed & compacted per the project specifications.
- Evaluate the project site for its ability to furnish satisfactory
replacement soil in quantities equaling and exceeding the estimated unsuitable soil
quantities. Based on this evaluation, define the project's base bid quantities and unit
price solicitations with regard to on- site or off- site borrow, or a combination thereof.
UNIT PRICES & BASE BID QUANTITIES OF ROCK OR UNSUITABLE SOIL
- The State construction Office stresses that realistic quantities (for
unsuitable soil and each class of rock excavation and, if applicable, in each prime
contract) must be explicitly defined for the base bids. These quantities should be stated
only once within the contract documents.
- Unit prices shall be solicited, for each class of rock or unsuitable soil,
for the adjustment of the final contract compensation up or down, depending upon the
quantity of such material actually encountered.
- If a project site's history or the boring results suggest that base-bid
quantity estimates are not likely to be accurate, the Forms of Proposal should include not
only a base-bid amount of rock excavation and unit cost for removal of additional material
in quantities close to the base-bid amount, but also should include unit cost
solicitations for specifically defined ranges of rock removal quantities. Reiterate that
compensation by means of these unit prices shall be the only compensation due the
Contractor when additional rock is encountered.
ROCK EXCAVATION OR UNSUITABLE SOIL NOT ANTICIPATED
- If, after study of the soil investigation report, rock excavation or
unsuitable soil are not anticipated, then base bid quantities of such work are not defined
in the construction documents.
- Solicit unit prices for classes of rock excavation or unsuitable soil that
reasonably might apply to the specific project. The Designer is reminded that, in absence
of a base bid amount of rock or unsuitable soil, the solicited unit prices will be
add-only unit prices. In other words, the price quotation will not be rationalized by the
possibility that the Contractor might have to credit the owner with that unit price, as he
might if encountered rock or unsuitable soil quantities were less than a defined base bid
amount. It is therefore particularly important that the Designer thoughtfully evaluate the
unit price quotations prior to recommending the award of the contract.
SITE DRAINAGE DIRECTIVES
- The site drainage must be designed to carry runoff without erosion of soils
on site and must not subject the facility to flooding at any time.
- When an overland emergency flow route is provided that will not subject the
facility to any flooding hazard, a storm return frequency of 10 years is to be used for
basis of the design. If an emergency flow route is not provided, a storm return frequency
of 100 years is to be used.
- Building foundation drains shall have points of outfall explicitly shown
the site drawings. Catchall phrases like "run to daylight" or "connect to
nearest storm sewer" are not acceptable.
|